Public Notice

Resuming Invitation to Participate in a Direct Procurement Procedure Purchase of technical counter-expertise services for the expert reports prepared by the contractor’s expert, as well as for the solutions proposed by him, for: Structure 1: Overpass over the A2 highway at km 53+069 (52+768) Structure 2: Overpass on the DN 4 national road at km…

Sulina Port – quay modernization

Quay on Sulina channel : 400 m Quay on maritime basin: 400 m oncrete platform adjacent to the quays: 28.800 m2 Acces road to the street network of Sulina: 650 m Dredging of the acces area for the quays https://consitrans.ro/wp-content/uploads/2021/07/Modernizare-Cheu-Sulina-25-06-2021.mp4 Sulina Port – quay modernization This feasibility study proposed and integrated modernization of the port…

A7 Highway – Ploiesti – Buzau

Highway Length: 63.25 km Overpasses: 40 Junctions: 6 Maintenance centers: 2 Parking-service spaces: 4 Status: Feasibility Study – finished Technical Project – in work https://consitrans.ro/wp-content/uploads/2021/03/consitrans-buzau-ploiesti.mp4 A7 Highway – Ploiesti – Buzau For this project we provided the analysis for the best highway positioning and layout, followed by the Feasibility Study and Technical project. Part of…

A1 Highway Lugoj – Deva

Highway Length: 28.6 km Overpasses: 9 Bridges: 2 Total Project Value – Lei: 562,730,583.80 RON Total Project Value – Euro: aproximativ 128,000,000 € Status: in execution Western Romania Providing Construction Supervision and Contract Management services for 28.6 km, Section 2, to improve traffic flow for travel, tourism and commerce. The Lugoj – Deva highway is…

Piers’ Modernization – Jiu River

Length: 11.76 m Pier Crossing Flood Defense Total Project Value – Lei: 7,385,600 RON Total Project Value – Euro: aprox 1,649,420 € Status: finished Gorj County, Southwestern Romania Providing preliminary to final construction drawing design and technical assistance for necessary rehabilitation and modernization of piers on the Jiu River. As a result of rains, the…

Braila Port Quays at Wharf 23 & Wharf 25

Braila Port – Danube River – Eastern Romania Providing preliminary to final construction drawing design and technical assistance to quays for port modernization. Part of the POST program (Operational Sectorial Transport Program) whose main objectives are to modernize and develop the national transport network in Romania. Completed 10 months ahead of schedule, Consitrans was responsible…

Ciurel Suspension Bridge

Bridge Length: 3.56 km Highway Length: 6.44 KM Bridges: 14 Total Project Value – Lei: 562,730,583.80 RON Total Project Value – Euro: aprox 128,000,000 € Status: in progress Bucharest, Romania Providing Construction Supervision and Contract Management services for the Ciurel Suspension Bridge, part of a much larger expressway project that will connect Independence Pier Road…